VI.
Evaluation of Participation
B. Efficiency Assessment59)
|
Planned
costs
€ |
Actual
costs
€ |
Deviation
€ |
| Rental of stand |
6.200 |
6.200 |
0 |
| Power Supply |
600 |
650 |
50 |
| Other basic costs |
1.250 |
1.290 |
40 |
| Construction |
8.450 |
12.100 |
3.650 |
| Equipment |
1.800 |
1.860 |
60 |
| Design |
1.900 |
2.300 |
400 |
| Depreciation |
600 |
600 |
0 |
| Stand Service |
1.750 |
1.750 |
0 |
| Communication |
2.200 |
2.350 |
150 |
| Transport |
1.300 |
1.300 |
0 |
| Waste disposal |
50 |
50 |
0 |
| Personnel costs |
5.350 |
6.000 |
650 |
| Travel costs |
3.100 |
3.300 |
200 |
| Other costs |
1.850 |
1.900 |
50 |
| TOTAL |
36.400 |
41.650 |
5.250 |
|