VI. Evaluation of Participation
B. Efficiency Assessment59)


 

 

 

Planned costs €
Actual costs €
Deviation €
Rental of stand
6.200
6.200
0
Power Supply
600
650
50
Other basic costs
1.250
1.290
40
Construction
8.450
12.100
3.650
Equipment
1.800
1.860
60
Design
1.900
2.300
400
Depreciation
600
600
0
Stand Service
1.750
1.750
0
Communication
2.200
2.350
150
Transport
1.300
1.300
0
Waste disposal
50
50
0
Personnel costs
5.350
6.000
650
Travel costs
3.100
3.300
200
Other costs
1.850
1.900
50
TOTAL
36.400
41.650
5.250